Notice to Proceed (NTP) May 17, 2022
Preliminary Design Submittal August 30, 2022
Initial Engineering (30% Design) Submittal February 21, 2023
Public Meeting #1 March 8, 2023
Constructability Plans (100% Design) Submittal September 28, 2023
Public Meeting #2 October 19, 2023
Production (Construction Documents) January 2024
FDOT Issues Revised Authorization to Bid October 2024
Revised Invitation to Bid Construction November 2024
Construction Begins May 2025